Tender ID (Unique No.) |
Tender No. |
Scope of Work |
Estimated Cost (in Rs.) |
Earnest Money Deposit (EMD) (in Rs.) |
Closing Date & Time of sale of Tender |
Date & Time of Opening of Tender |
Department |
| DTL-266-051007 | DTL/DGM(O&M-II)/GIS/GT NO. 204 |
International Competitive Bidding (ICB) for Design, Engineering, Manufacture, Transportation to Site, Insurance, Storage, Erection, Testing & Commissioning of 220 kV GIS Substation having 220KV & 66KV GIS equipments , 160MVA power transformer and other substation equipments at IGI Airport, New Delhi (India) on turnkey basis. |
1054472653/- | 21089500/- |
Upto 04.00 PM on25.01.08 |
At 11.30 AM on28.01.08 |
G.M.(CWGP-1) |
| DTL-282-161007 | DGMSSC-I/07-08/T-04 |
Hiring of Hydraulic Tractor Trailer and Transportation of 1x100 MVA 220/66-33/11 KV Pr. Tr. (C.G.L. make) including Loading, Unloading & Dragging from Gas Turbine Station to 220KV S/Stn. Vasant Kunj. |
6,17,405/- |
12,500/- |
Up to 05.00 PM on 07.01.08 |
At 11.30 AM on08.01.08 |
Construction |
| DTL-319-141107 | Mgr.(T)O&M-II-A/ET-1/T-1/07-08/1 | overhauling/conditioning, testing & commissioning of 20 MVA 66/11 KV Power Transformer, at site including arresting of oil leakage & drying out of Tr. as per scope of work annexed here with as annexure installed at 220 KV, Grid Sub Station Sarita Vihar. |
4,86,689/- |
9734/- |
Up to10.30 AM on24.12.07 |
At 11.30 AM on 24.12.07 |
O&M |
| DTL-330-161107 | DTL/Mgr(T)400/220KV(O&M)Lines-II/T-5 /2007-08 | Hot Line washing of disc insulators of 400KV D/C Tower Lines of DTL in NCT of Delhi | 20,00,000/- | 40,000 /- | Up to 04.00 PM on 01.02.08 |
At 11.30 AM on 04.02.08 |
O&M |
| DTL-335-221107 | DTL/DGM(TL)C/T-125/07-08 |
Annual Contract for day to day maintenance of internal electrification work at Defence Colony, Lodhi Road, JNU, Mehrauli Store, Okhla Training Centre of DTL. |
5,22,792/- | 10,456/- | Up to 05.00 PM on 17.12.07 |
At 11.30 AM on 18.12.07 |
Construction |
| DTL-336-221107 |
|
Erection, Testing & Commissioning of Five No. 66KV bays at 220KV S/Stn. South of Wazirabad | 8,47,664/- | 17,000/- | Up to 05.00 PM on 28.01.08 |
At 11.30 AM on 29.01.08 |
Construction |
| DTL-343-231107 | T/SP-I/2007/09 | Procurement of 30KV,10KA Las | - | 9200/- | Up to 05.00 PM on 18.12.07 |
At 11.30 AM on 19.12.07 |
Store |
| DTL-344-231107 | T/SP-I/2007/03 | Procurement of 33KV PTs | - | 5500/- | Up to 05.00 PM on 18.12.07 |
At 11.30 AM on 19.12.07 |
Store |
| DTL-355-301107 | T/SP-I/2007/23 |
Procurement of 33KV, 1x1000sq.mm, Aluminum Conductor XLPE Cable. |
- | 97,000/- | Up to 05.00 PM on 25.12.07 |
At 11.30 AM on 23.01.08 |
Store |
| DTL-361-061207 |
Cleaning of Shakti DeepBuilding at Jhandewalan of DTL |
3,16,550/- | 6350/- | Up to 03.00 PM on 04.01.08 |
At 11.30 AM on 08.01.08 |
Civil | |
| DTL-365-111207 | F.DTL/Mgr(T)O&M II /MLI/07-08/01 |
Repairing testing erection and commissioning of 1No .25MVA ,66/11 BBL make power transformers lying at 220KV Grid SubStation Mehrauli. |
79,53,535/- | 160000/- | Up to 05.00 PM on 07.03.08 |
At 11.30 AM on 10.03.08 |
O&M |
| DTL-366-111207 |
|
Supplying and Filling of Fly ash and earth at 400 KV S/Stn. Mundka. | 8,39,83,200/- | 16,79,700/- | Up to 03.00 PM on 31.12.07 |
At 11.30 AM on 21.01.08 |
Civil |
| DTL-368-121207 | DTL/MGR.(T)400/220kV(O&M)LINES-I/T-6/2007-08 | Replacement of single disc insulator strings with double insulator strings on existing 220 kV D/C Transmission Line Towers of DTL across major road crossings in NCT of Delhi | 13,07,200/- | 26,200/- | Up to 04.00 PM on 07.03.08 |
At 11.30 AM on 10.03.08 |
O&M |
| DTL-371-131207 |
Internal finishing works of quarters at New/old Kilokri Colony in lieu of special Occasion (i.e. Wedding etc.). |
2,56,000/- | 5150/- | Up to 03.00 PM on 20.12.07 |
At 11.30 AM on 24.12.07 |
Civil | |
| DTL-372-131207 | DGM SSC-I/07-08/T- 07 | Estimate for the Overhauling, Erection, Testing & Commissioning of One No. 100MVA, 220/66-33KV/11KV Pr. Transformer at 220KV S/Stn. Vasant Kunj. | 7,48,781/- | 15,000/- | Up to 05.00 PM on 24.03.08 |
At 11.30 AM on 25.03.08 |
Construction |
| DTL-374-181207 | Development of yard in 315 MVA Tr-4 bay including incommer 220 KV bay at 400 KV S/stn Bamnauli | 46,87,900/- | 93,800/- | Up to 03.00 PM on 11.01.08 | At 11.30 AM on 15.01.08 | Civil | |
| DTL-375-181207 | Development of 220KV switchyard and other works at 220KV S/Stn Kanjhawala | 54,23,500/- | 1,08,500/- | Up to 03.00 PM on 11.01.08 |
At 11.30 AM on 15.01.08 |
Civil | |
| DTL-376-181207 | DGM(T)C/T-33/07-08 | Supplying and placing flower guldasta in the offices of Directors/Other offices at Shakti Sadan Building and Lodhi Road Offices | 1,73,000/- | 3,500/- | Up to 03.00 PM on 27.12.07 |
At 11.30 AM on 28.12.07 |
Civil |
| DTL-377-191207 |
|
Erection, Testing & Commissioning of 3 nos. 220 KV feeder bays with associated equipments at 220 KV S/Stn Shalimar Bagh. | 6,49,235/- | 13,000/- | Up to 05.00 PM on 04.03.08 |
At 11.30 AM on 05.03.08 |
Construction |
| DTL-378-191207 |
|
Overhauling,Erection, Testing & commissioning of 1x100 MVA Pr. Tr. at 220 KV S/Stn. Shalimar Bagh. | 7,32,996/- | 14,700/- | Up to 05.00 PM on 26.03.08 |
At 12.00 Noon on 27.03.08 |
Construction |
| DTL-381-201207 | C/O Tr. Foundation (100 MVA) along with gantry and other associated foundation at 220 KV S/stn. Vasant Kunj | 24,04,200/- | 48,100/- | Up to 03.00 PM on 18.01.08 |
At 11.30 AM on 22.01.08 |
Civil | |
| DTL-382-201207 | Construction of gantry, equipment foundation and supply, erection of 66KV gantry G.I.M.S. structure for 5Nos. 66Kv bay at 220Kv sub station Park Street | 32,15,000/- | 64,300/- | Up to 03.00 PM on 18.01.08 | At 11.30 AM on 22.01.08 | Civil | |
| DTL-385-201207 | DGM(T)C/T-36/07-08 | Face lifting of balance Blocks ( 1 of Type III & 3 of Type IV ) at New Kilokri Colony DTL. |
6,35,800/- |
12,750/- | Up to 03.00 PM on 18.01.08 |
At 11.30 AM on 22.01.08 |
Civil |
| DTL-398-271207 | DTL/MGR.(T) 400/220KV(O&M) LINES-II/T-7/2007-2008 | Attending to the Break-downs and General Maintenance works on 400/220KV Double Circuit Transmission Lines of Delhi Transco Limited | 20,000,00/- | 40,000/- | Up to 04.00 PM on 01.02.08 |
At 11.30 AM on 04.02.08 |
O&M |
| DTL-402-311207 | DGM(T)C/T-37/07-08 | Cleaning and Sweeping of Shakti Sadan Bldg. | 4,16,700/- | 8400/- | Up to 03.00 PM on 21.01.08 |
At 11.30 AM on 25.01.08 |
Civil |
| DTL-403-020108 | T/SP.II/2007/28 | HW Fitting for ACSR Zebra conductor and 19/2.5mm Earthwire | 70.31 lacs | 140620/- | Up to 05.00 PM on 24.01.08 |
At 11.30 AM on 25.01.08 |
Store |
| DTL-419-080108 | Providing and laying brick on edge flooring on internal switchyard road berms and other repairing works at 220KV S/Stn. Shalimar Bagh | 7,73,412/- | 15,470/- |
Up to 03.00PM on 01.02.08 |
At 11.30AM on 05.02.08 |
Civil | |
| DTL-421-090108 | DTL/MGR.(T) 400/220KV(O&M)LINES-I/T-8/2007-2008 |
Hiring the services for Thermo-vision scanning of 400/220 kV transmission lines of Delhi Transco Limited |
10,00,000/- | 20,000/- |
Up to 04.00PM on 15.02.08 |
At 11.30AM on 18.02.08 |
O&M |
| DTL-430-150108 | DTL/DGM(TL)C/T-128/07-08 | Providing earthing & New Electrical Wiring at Timarpur Colony & Rewari Line staff Colony (DTL). | 5,55,506/- | 11,200/- |
Up to 05.00PM on 07.02.08 |
At 11.30AM on 08.02.08 |
Construction |
| DTL-431-150108 | T/Mgr(T)O&MII-A/OKL/FT-2 /07-08/01 | Supply of 168KVAR ,6.35KV , 26.46A Internal Fuse type Capacitor Cells for 5.04MVAR 11KV cap bank at 220KV S/S, Okhla. | 2,95,642/- | 5,920/- |
Up to 05.00PM on 22.02.08 |
At 11.30AM on 25.02.08 |
O&M |
| DTL-434-150108 | DTL/DGM(TL)C/T-126/07-08 | Annual Contract for day to day maintenance of internal electrification work at Jhandewallan office of DTL. | 4,38,388/- | 8,800/- |
Up to 05.00 PM on 07.02.08 |
At 11.30AM on 08.02.08 |
Construction |
| DTL-435-150108 | T/Mgr(T)O&MII-A/OKL/FT-2/07-08/02 |
Hiring of Services for Thermo Vision Scanning of various 400 KV & 220KV Grid S/Stn. equipments along with man power & instrument for One Year on Bi-Monthly basis under DGM (O&M)-II circle. |
14,44,050/- | 28,900/- |
Up to 05.00 PM on 22.02.08 |
At 11.30AM on 25.02.08 |
O&M |
| DTL-442-180108 | GM(IT)/07-08/T-3 | Comprehensive annual maintenance contract of computers & other equipment of DTL for year 2008-09 | 13,52,085 /- | 27,000 /- |
Up to 05.00 PM on 07.02.08 |
At 11.30AM on 08.02.08 |
I.T |
| DTL-443-180108 |
|
Erection, Testing & Commissioning of One No. 220KV bay & One No. 66KV Incomer bay for 100 MVA Power Transformer at 220 KV Sub. Station, Vasant Kunj. | 4,52,173/- | 10,000/- |
Up to 05.00 PM on 24.03.08 |
At 11.30AM on 25.03.08 |
Construction |
| DTL-445-220108 | Sweeping/Cleaning of Civil office and 220 KV Grid sub station building at CGO complex Lodhi Road. | 1,51,500/- | 3,030/- |
Up to 03.00 PM on 15.02.08 |
At 11.30AM on 19.02.08 |
Civil | |
| DTL-457-280108 |
(Tender is Withdrawn)
|
Appointment of I T Consultant | 17 Lakh | 34,000/- |
Up to 10.00 AM on 28.02.08 |
At 11.30AM on 28.02.08 |
I.T |
| DTL-461-310108 | Erection, Testing and Commissioning of shifting of portions of existing 220 KV D/C Tr. Lines due to construction of Bridge and its approaches over River Yamuna Downstream of existing Bridge at Wazirabad, Delhi.. | 430.89 lacs | 8.65 Lacs |
Up to 05.00 PM on 27.02.08 |
At 11.30AM on 28.02.08 |
Construction | |
| DTL-467-040208 |
F.DTL/206/F.10/Q-17/2007-08/ Mgr(BWN)/549
|
Operation & maintenance of fire-fighting system at 400 kV S/Stn. Bawana | 95,220/- | 2,000/- |
Upto 04.30 PM on 18.02.08 |
At 11.00AM on 11.03.08 |
O&M |
| DTL-468-040208 | F.DTL/206/07-08/MGR.(O&M)-VI/T-03 |
Attending oil leakage of 220KV class NGEF make 100MVA power transformers at 220KV S/stn. Kashmere Gate. |
3,16,855/- | 6400/- |
Upto 04.00 PM on 11.04.08 |
At 11.30AM on 15.04.08 |
O&M |
| DTL-469-050208 | T/SP.II/2007/12 |
220 KV, outdoor type capacitor voltage transformer of ratio (220KV/√3) /(110V/√3)/(110V/√3)/110V(27Nos.) AND (220KV/√3)/(110V/√3)/(110V/√3) /(110V/√3) (28 Nos.) alongwith terminal connectors suitable for ACSR ZEBRA conductors |
2.09 crores | 4,18,000/- |
Upto 05.00 PM on 28.02.08 |
At 11.30AM on 29.02.08 |
Store |
| DTL-470-050208 | T/SP.I/2007/31 | Procurement of 33KV, CTs of different ratio | - |
28,400/- |
Upto 05.00 PM on 28.02.08 |
At 11.30A |